Historical Documents

The following table provides access to surveys, presentations, and schematics related to the Bush-Wellborn intersection improvement project.

These documents are organized into two categories:

Pre-funding (before 2023):
This section includes tasks and documents completed prior to the project’s full funding. These historical documents provide context and reference to earlier phases of the project. Please note that since these documents were developed, additional information has been gathered, and the project plans have evolved.

Post-funding (after 2023):
This section contains documents developed after the project received full funding in 2023. These reports may be marked as “historical reference” or “current information.” Even though some of these materials are recent, the project has seen rapid development, and new insights continue to shape the direction of the work.

Documents

Survey

Pre-Funding

A survey was conducted from April 2017 to July 2017, and over 4,100 survey responses were analyzed. The purpose of the survey was to gain an understanding about:

  • The importance of construction or design features in any future intersection improvements
  • Change in travel habits during construction
  • Priority of elements throughout the construction process
  • Specific suggestions for future intersection design and construction process.

Summary of survey results
Full report of survey results

Post-Funding

A survey was conducted from March 2024 to December 2024 and received about 3,000 survey responses and over 3,000 comments from four free-response questions. The purpose of the survey was to gain an understanding about Bryan-College Station traveler information and construction needs. Key takeaways from the survey indicate respondents want:

  • Extensive communication that goes beyond what is traditionally done.
  • Information about construction phasing, before construction begins and throughout construction.
  • Construction phasing effectively communicated through different forms, and readily available so the public can choose how to best consume it.
  • Timely and accurate information.
  • Coordination among the community agencies so the public has various travel options.
  • Construction done differently from past community projects, specifically FM 2818.

Presentation of survey results
Summary document of survey results

Schematics

Pre-Funding

TxDOT received approvals to move ahead with a proposed design in 2007, over 15 years ago. Below is a schematic of the approved design.

Pre-Funding – Intersection schematic – 2008

Pre-Funding – George Bush Cross-Section – 2008

Pre-Funding – Wellborn Cross-Section – 2008

Post-Funding

TxDOT is working towards finalizing a design and we hope to show it to you by late 2025.

Stakeholder Communcation Team

Pre-Funding

Stakeholder Communication Team was not created prior to funding.

Post-Funding

The Stakeholder Communication Team was established to increase the level of outreach to the public before and during the construction project.
Meeting #1: November 13, 2024 – Presentation